Construction of Business Bay Sales Centre

Project Planning Engineer, Al Habtoor Engineering Enterprises, Construction of Business Bay Sales Centre, Construction of 12 Towers @ Business Bay and Construction of Commercial Tower @ Dubai Marina, Dubai,

START Date: 
October, 2005
END Date: 
February, 2009
  • Preparation of contractual programs – Clause 14.1 for the awarded projects, in co-ordination with the project manager of that respective project, and assigning the quantities and manpower in the program for following up during updating, time wise and quantity wise.
  • Preparing the Internal Target program, for the internal use of Al Habtoor Company, with same starting date and 2 month or less from the Clause 14.1 finish date.
  • Updating the Clause 14.1 & Target Programs of nearly 4000 activities.
  • Recovery Programs.
  • Preparing Weekly & Monthly