Website Upgrade Incoming - we're working on a new look (and speed!) standby while we finalise the project

China

Assistant Engineer at site, CNOOC, CSPC Nanhai Petrochemical Complex Project, Huizhou, Guangdong, China

START Date: 
May, 2003
END Date: 
May, 2004

Assistant engineer for civil structure field construction in Shell & CNOOC project in Guangdong, China

Junior Planner/ site report, AMEC Foster Wheeler, CSPC Nanhai Petrochemical Complex Project, Huizhou, Guangdong, China

START Date: 
June, 2004
END Date: 
September, 2009

Scheduling, planning, reporting for CSPC project, 3M SCIP Adesive project, Novartis Changshu project, DOW & Shenhua Coal to chemical FSR project

Assistant Resident Engineer, Power Engineering Associates Limited, Barytes Crushing Plant, China, Wuchow

START Date: 
March, 1981
END Date: 
June, 1982

Assistant Resident Engineer, reporting to the Resident Engineer, responsible for the construction of a Mineral Crushing Plant in Wuchow, China. Responsible for all incoming equipment and materials and trans shipment from UK via Hong Kong.

Planner, Air Products, China, Petrochemical Complex Plant in Chengdu, Sichuan

START Date: 
October, 2009
END Date: 
December, 2010

Master Scheudle development and maintain, regular schedule review meeting, progress reports, trend analysis

Regional Manager PMO (PM Competence Development), Huawei Technologies Co., Ltd, GTS PMO, China

START Date: 
April, 2006
END Date: 
August, 2007

Worked in Shenzhen China at Huawei HQ PMO. 

Role was the development and enhancement of PMO Process, Procedures and PM Competency development