Senior Planner , TURNER & TOWNSEND, Asia, Chevron Chuandongbei Gas Project

START Date: 
April, 2014
END Date: 
April, 2016
  • Built up the WBS, weighting system, level 1-4 master schedules baseline, Manpower Histogram and progress curves for progress reports. Built up the project progress measure system.
  • Set up resourcing plans for the overall and individual project phases, track and monitor master schedule. Fish-bone milestone schedule preparation and update.
  • Weekly update each discipline’s progress S-curves and regular reports preparation and issue to team.
Experience Hours (Planning & Scheduling): 
4200
Experience Hours (Forensic Analysis): 
600

Senior Planner, Turner towsend, Chevron ChuanDongBei Gas Project

START Date: 
November, 2014
END Date: 
February, 2016
  1. Implement Project Planning & Scheduling strategy, plans and procedures.
  2. Coordinate the development and implementation of project Work Breakdown Structures (WBS).
  3. Promote and maintain the overall integration and integrity of contractor schedules within the Program suite of project schedules.
  4. Provide interface and quality assurance to Project functional groups and contractors regarding the tracking and reporting of schedule performance.
  5. Support the Project Team in the implementation of an
Experience Hours (Planning & Scheduling): 
2700
Experience Hours (Cost Management): 
2700
Experience Hours (Forensic Analysis): 
2700