Channel Tunnel Rail Link (C320)

Civil Scheduler, Kier Construction, Channel Tunnel Rail Link (C320)

START Date: 
October, 2000
END Date: 
September, 2002

Channel Tunnel Rail Link, Contract 303, Dagenham. Value £23 million. Construction of 3 new road bridges over the live railway and the diversion of a river beneath the railway. Responsible for medium and long term construction planning, possession planning, production of reports including earned value measurement and determining the effect of change on the project. Planning support for bid preparation.

Experience Hours (Planning & Scheduling): 
3800
Experience Hours (Forensic Analysis): 
1100