Blackburn Meadows Power Station

Senior Delay Planning Consultant, BAMN, Blackburn Meadows Power Station

START Date: 
June, 2013
END Date: 
September, 2013

Currently contracted to Systech International in London.

 My current position is as Senior Planner working in Sheffield for 3 months on a new Power plant which is overspent and in Delay. Primarily though I am repsonsible for building up the Delay Analysis for a number of buildings on this civils project. This has meant researching as built data from programmes and site diaries, monthly and weekly meeting reports. I have demonstrated the Planned v As built position for the design and also Construction elements of the project. 