Biomass Project - Drax Power Station

pipefiter, National Grid UK, Biomass Project - Drax Power Station

START Date: 
August, 2013

Spent most of my working life in the UK on various compressor stations, AGI's and pipelines for National Grid's Pipeline Maintenance Centre in Derbyshire.

Developed a keen interest for pipe fitting in my early days at National Grid, learning from some of the most experienced people in the industry.

Site Support Engineer, Alstom, Biomass Project - Drax Power Station

START Date: 
April, 2008
END Date: 
November, 2010

April 2008 – November 2010: Alstom Power Boiler Retrofits

During this period I was working as a Site Support Engineer at Drax Power Station. The project scope is the install and commissioning of the largest co-firing biomass system to date.

Key Responsibilities:

  • Programme; creating, updating, maintaining and forecasting.
  • Reviewing sub-contractors programmes and Monthly Reports.
  • Monitoring and evaluating the progress of the Works.