Berri Gas Plant HPDGA and SRU expansion

Project Controls Engineer, Mohammad Al Mojil Group, Berri Gas Plant HPDGA and SRU expansion

START Date: 
May, 1998
END Date: 
May, 2000

 

§  Prepare and update detailed work schedules for some of the project’s critical activities like System Pressure Testing Schedule and Plant Shutdown Piping Tie-In Schedule using the Primavera Project Planner.

§  Monitor, quantify and report the work accomplishments, manpower and expended man-hours in my area of responsibility

§  Quantity take-off for progress reporting and billing purposes