ATR-Pak-Arab Refinery Ltd. (MCR)

Turn Around Planning Engineer, Descon Engineering Pvt. Ltd, ATR-Pak-Arab Refinery Ltd. (MCR), Pakistan. Feb. 2007 – Apr. 2007 Annual Turn Around/Overhauling

START Date: 
March, 2007
END Date: 
June, 2007

Responsibilities Highlights: Descon Engineering Pvt. Ltd hired my services in the capacity of Turn around Planning Engineer, for the PARCO-ATR.In this particular position, I was personally responsible for defining and proposing turn around scope of work, scheduling & planning, making work progress reports, making of inspection reports and dossier for client for following equipment:

Experience Hours (Planning & Scheduling): 
400
Experience Hours (Cost Management): 
150
Experience Hours (Forensic Analysis): 
100