Responsible for Establishment/Monitor/Control (but not limited) to the following
1. Detailed Construction Schedule for Main Civil Works(Level 4) in P6
2. Detailed Construction Schedule for Underground Piping works in P6
3. Progress Measurement System
4. Weekly/Monthly Progress Reports, Weekly/Monthly Lookahead schedule
5. Site Budget, Monthly Cost Tracking(CPI, SPI) Reports using JD Edwards, Ezware(Custom made Timesheets software)
6. Productivity Reports/Analysis