Arzew Desalination and Power Plant Project

Technical Office Engineer, Planning & Cost Control, Alsim Alarko, Arzew Desalination and Power Plant Project, Oran, Algeria

START Date: 
January, 2004
END Date: 
June, 2004

Technical Office. Planning, payment certificates of client and subcontractors, cost control (6 months).

Project details:Scope contract value US$7,000,000. Civil works & erection of steel structures.

●      Primavera scheduler,

●      Due reports for client, Weekly, monthly reports to management,