Aircraft Alliance for new Queen Elisabeth Class.

Commissioning Planner, BAE SYSTEMS (Naval Ships), Aircraft Alliance for new Queen Elisabeth Class.

START Date: 
July, 2015
END Date: 
January, 2016

(Contractor)

Commissioning Planner on 1st of Class QNLZ Royal Navy Air Craft Carrier.

Working with the Lead Commissioning Planner to deliver a very complex schedule.

Introduced Structured Weekly Progress Collation and Reporting and Assisted with Management Reporting.

Experience Hours (Planning & Scheduling): 
1000

Senior Planning Engineer, C&D Industries Ltd, Aircraft Alliance for new Queen Elisabeth Class.

START Date: 
September, 2009

Senior Planner.

Plan using Microsoft 2007 and P3 the Design, Manufacture, Installation and Commissioning of HVAC for 2 Aircraft Carriers.

Liaise with 5 Dockyards concerning the Installation of HVAC

Integrate 24 various plans of differing Modules being built in 5 Shipyards for completion in Rosyth Dockyard.

Produce fully costed and resourced level 4 plans.

Report progress via scorecards iaw approved procedures.

Detail Project Management Plan and Responsibility Matrix for internal use.