ACCRO II CORPOVEN

Planning & Project Control Manager, CONSORTIUM TECHNIP / DIT HARRIS, ACCRO II CORPOVEN

START Date: 
January, 1993
END Date: 
May, 1995

Planning and Control Manager Reporting to the Project Director expansion of the Train 3  and 4  of Jose Plant, consisting of separators towers, substation expansion, compressor and cooler installation, plant pipeline installation.