1. Preparation of Baseline Schedule with Resource & Cost Loading
2. Allocating Time Periods for Subcontractor, as per the Maincontractors Shedule and approving their programme of work.
3. Montioring Site Progress and Preparation / Submission of Weekly / Monthly Progress Report
4. Attending Progress Meeting and listing out the Critical / Near Critical activities to Client / Consultant
5. Preparation & Submission of Interim / Final EOT Claims