Site Engineer, Metro Stonerich Corporation, SM Planetarium & SM Pavillion

START Date: 
December, 2006
END Date: 
June, 2008

•        Reporting to the Project Manager and carrying out his directives with respect to field operations. Being thorough familiar with the requirements of the General Contracts, and thereby identifying changes and conflicts that are beyond the scope of company responsibility.

•        Studies and interpret structural and architectural drawings in detail to have a good judgment in site operations. Developed the installation plan and schedule with the Project Manager and Project Engineer.

Experience Hours (Planning & Scheduling): 
500
Experience Hours (Cost Management): 
500
Experience Hours (Forensic Analysis): 
100

Site Engineer, Micron Electrical - Bangalore, Bharati Airtel Office

START Date: 
November, 2007
END Date: 
June, 2008

I was assigned to manage a site for Electrical Work.  

Experience Hours (Planning & Scheduling): 
400
Experience Hours (Cost Management): 
100

Site Engineer, Rani Construction, Construction of Commercial Malls & Residential Villas

START Date: 
May, 2000
END Date: 
March, 2001

Supervision incharge of the construction sites of the firm, managing day-to-day activities of site, controlling labors and equipment.

Site Engineer , Rustom Construction co., Saïda Complex (24 residential bldgs.)

START Date: 
July, 1996
END Date: 
January, 1999
Supervised and managed daily construction activities of Saïda Complex which included 24 residential bldgs. ($ 12 M)

Site Engineer, Adhi Oman LLC, Grand mall muscat

START Date: 
July, 2007
END Date: 
August, 2009

Key Role  :

ü  Ensures activities during assigned project execution are consistently performed in compliance with the established procedures.

ü  Making a planning/ Target Schedulebased on time frame of working, quantity and methodes.

ü  Arrange the resourses of materials, labors and equipment to support the finalizing of the work.

Site Engineer, Al-Emara Al-Haditha Company, 1 Rashid Bank Building with basement and safe rooms 4 stories, Baghdad 5- Najaf gypsum facto, Karbala 2- Dar Alsalam Bank with basement and safe rooms, Karbala 3- Communication tower 76 m in height south oil com

START Date: 
September, 2001
END Date: 
February, 2004

Site Engineer:

Myrole and responsibilities in Projects:

1.      Supervising the functions and responsibilities oftechnicalsupervisors.

2.      Involved with the project manager to establish a program implementation schedule which shows Cascade implementation steps.

Experience Hours (Planning & Scheduling): 
1400
Experience Hours (Cost Management): 
1600
Experience Hours (Forensic Analysis): 
4000

Site Engineer, Memar, Residential and Industrial buildings

START Date: 
January, 1995
END Date: 
January, 1996

Supervised construction of residential and industrial projects to make sure that work was being done according to engineering drawings and specifications. Communicated progress and any important issues to senior management.

Experience Hours (Planning & Scheduling): 
2000
Experience Hours (Cost Management): 
1000

Site Engineer, Gammon Pakistan, Construction of Cement Plant, Roads & Bridges

START Date: 
February, 1996
END Date: 
August, 1997
Supervised construction of large RCC structures at Fauji Cement Plant Project (Pakistan) and ensured their timely completion as per design and specifications. Prepared work methods for miscellaneous construction activities. Prepared and verified monthly bills and bar bending schedules.
Experience Hours (Planning & Scheduling): 
2000
Experience Hours (Cost Management): 
1000

Labourer, Planners assistant, QS assistant, Site Engineer, ARC, Fairclough Construction, John Laing Construction, M&R Bean, William Ellis Ltd, General builders, Hastings Conquest Hospital, Housbuilding, Sea Defences Hastings, Traflagar Place Brighton

START Date: 
November, 1989
END Date: 
September, 1991

As a college student I managed to secure work most holidays with Major Contractors working close to my home adn took a year out working as a labourer for a small local builder.  Projects worked on include Site Engineer - setting out for Laing on a new hospital construction in Hastings, setting out Engineer and planning for ARC during reconstruction of sea defences in Hastings, owrking in the estimating and planning departments for William Ellis Ltd Etchingham, speculative and council house builder, tender reponses and claims collation for Fairclough in Maidstone, Planning and site supe

Experience Hours (Planning & Scheduling): 
500
Experience Hours (Cost Management): 
500
Experience Hours (Forensic Analysis): 
550

Site Engineer, M/S. J. M. Mhatre Gov. reg. contractor, Panvel - JNPT Railway Doubling

START Date: 
June, 2004
END Date: 
May, 2006

ü  Execution of Major & minor culvert with layout, formwork, concreting etc

ü  Execution of Controlled blasting work with safety

ü  Execution of Embankment

ü  Preparation of Bar bending schedule.

ü  Maintaining contractors MBs