Senoir PMCS Engineer

Senoir PMCS Engineer, Turner Construction International LLC, Al Raha Beach Developement

START Date: 
January, 2010

• Prepared a Fully detailed program for the work for coordination purpose.

• Reviewed the contractor detailed cost and resource loaded programme of work which consists of the following: Marina and beaches work, roadwork and utilities network.

• Directly responsible for Preparation of the Al Dar COO presentation and the monthly executive report for Al Dar top management.

• Directly responsible for preparation the Extension of time recommendation for client using prospective and retrospective analysis time impact and windows technique.

• Directly responsible fo