Project Interface Manager, CMC/ITD/SONGDA, NamTheun 1 Hydro Power Project

START Date: 
May, 2018

Interface Manager

Conctract A Interface Manager of NamTheun 1 Hydro Power Project

Experience Hours (Planning & Scheduling): 
1200

Project Interface Manager, Oman Oil Company Exploration and Production, Musandam Gas Plant (MGP)

START Date: 
September, 2010

Project Interface Manager, Oman Oil Company E&P (OOCEP)

Muscat, Oman— Sep 2010-Present

Responsible for the overall management of technical and non-technical interfaces for the Musandam Gas Plant Project (MGP).  MGP is a 1 blnUS$ oil and gas processing plant that will process well fluids from the existing Bukha offshore fields.

Position Dimensions:

●     1blnUS$ (Gross) budget