Project Controls/Planning Lead Supv

Project Controls/Planning Lead Supv, Chevron, TCO Future Growth Project/Well pad Pressure Management

START Date: 
May, 2014
END Date: 
June, 2020

Planning /Lead responsible for the functioning of the Integrated Project Controls Team. Developing of Project Controls/Planning Procedures and the Project Execution Plan. Responsible for development of the Overall Programmed Schedule and approving of Master Baseline. Responsible for Managing all Contractor Planning. Responsibility was inclusive of approving Contractor Baseline Schedules and monitoring Progress and reporting overall progress up to the Project Director.

Experience Hours (Planning & Scheduling): 
2000
Experience Hours (Cost Management): 
2000
Experience Hours (Forensic Analysis): 
1500