Project control specialist

Project control specialist, Fluor Daniel BV, Olefin 2 Kuwait (OL2K) Project

START Date: 
January, 2005
END Date: 
April, 2006

 

-       Responsible for monthly progress status report of materials procurement, contracts development and engineering manhours.

Experience Hours (Planning & Scheduling): 
2450
Experience Hours (Cost Management): 
2450

Project control specialist, Asia Project-Company, Project Control Specialist at

START Date: 
January, 2010
END Date: 
November, 2011

MS Project files to P6 files

Manpower Resource analysis

Develop the Summary Schedule for Owner Modify the Master Schedule and Work Plan Develop the CBS/COA(Cost of Account)

Procurement Schedule(Import and Local) match to Construction Schedule Develop the Construction Baseline Schedule

Engineering Schedule Review

Project control specialist, LyondellBasell, Clinton Complex

START Date: 
January, 2017

Responsible for capital projects FEL scheduling and resource analysis.

Development of contractor reporting processes.

Review team and contractor costs and progress across a suite of projects for the Clinton facility.

Experience Hours (Planning & Scheduling): 
200
Experience Hours (Cost Management): 
200
Experience Hours (Forensic Analysis): 
200

Project control specialist, Fluor Arabia Limited, MA’ADEN ALUMINIUM COMPLEX PROJECT

START Date: 
February, 2012

The USD 10.8Billion Ma’aden Aluminum Project (Joint venture between Alcoa & Ma’aden) consists of Alumina Refinery, Bauxite Mines, Rolling Mill, Smelter, Carbon, Reduction, Tankage, Calciner and Sea port area, 12KM of 40” Oil transporting pipeline, Power Substations, Water treatment, Security and Communication Systems, Buildings and development of Integrated Infrastructure for all Utilities.

Project Control Specialist, Honeywell International, Borouge 3

START Date: 
June, 2002

Project Management              

·          Planning (S-Curve, PERT & CPM), Scheduling (MS Project & Primavera), Resourcing, Progress Updating, Controlling and Billing Activities.

·          Earned Value Analysis

Project Control Specialist, RekindWorleyParsons, Surface Facility Construction

START Date: 
March, 2012

Summary Experiences

Lead and supervise a project controls group consisting of Schedulers, Cost Engineers, Quantity Surveyor, and Document Controllers in order toprovide Project Controls Services to Client(resources management, project/construction schedule development, cost control and forecasting, schedule control and forecasting document management).Assigned to under-performing handling Operational & Maintenance/Small Caps for Chevron’s Duri Oilfield.

Project Control Specialist, --, --

START Date: 
March, 2012