Manager (Planning & Scheduling)

Manager (Planning & Scheduling), Reliance Industries Limited, Jamnagar Export Refinery project

START Date: 
November, 2006
END Date: 
April, 2010

 

Prepare WORK BREAKDOWN STRUCTURES (WBS) for the project & initial network of activities in consultation with Subject Matter Experts (SMEs) for the project programme in Primavera 

Prepare master/baseline schedule for the project & and review the schedule submitted in the bid and prepare the detailed baseline schedule (L1 to L4) during design and construction stages for the project. 

Preparing weekly and monthly progress reports based on data captured during execution on weekly/monthly basis.