Junior Site Planning Engineer

Junior Site Planning Engineer, Sime Darby Engineering, EPCI of Bunga Raya E Platform; EPCIC of Bunga Orkid A Platform

START Date: 
January, 2004
END Date: 
May, 2007

1. Monitored and maintained progress report

2. Prepared weekly and monthly report

3. Prepared planning package for project and tendering 

Experience Hours (Planning & Scheduling): 
5500

Junior Site Planning Engineer, Aegek SA, Highway construction in sector of E75

START Date: 
January, 2004
END Date: 
December, 2005

Worked as a junior site planning engineer, in the by-pass construction of the Highway in the area of Kamena Vourla in Central Greece, a project of a € 84.200.000,00 budget, part of the National Roadway Network (E75).

Junior Site Planning Engineer, Aegek SA, Highway construction in sector of E75

START Date: 
January, 2004
END Date: 
December, 2005

Worked as a junior site planning engineer, in the by-pass construction of the Highway in the area of Kamena Vourla in Central Greece, a project of a € 84.200.000,00 budget, part of the National Roadway Network (E75).

Junior Site Planning Engineer, Eversendai Engineering Saudi, Cemestero Saudi arabia co, KAFD Riyadh

START Date: 
August, 2011
END Date: 
December, 2013
 Assisted the project managers in identifying the right resources for a project team, tracking resource allocation and resource usage to minimize, over and under utilization.  Identified & built project teams by using resources that belong to the Enterprise Resource Pool.  Performed in-depth reporting & analysis against completed projects, in-progress projects & resource availability.  Responsible for planning Day to Day erection Activity and Allocate resource accordingly.  Coordinated with Client, Designer, Subcontractors, Quantity Estimation, Preparing Monthly Payment & Control in D