Website Upgrade Incoming - we're working on a new look (and speed!) standby while we deliver the project

Graduate Engineer

Graduate Engineer, Planning Engineer, Transmanche Link (TML), Channel Tunnel

START Date: 
August, 1988
END Date: 
December, 1993

Measurement and setting out Engineer on Terminal.

Terminal programme developemnt and progress reporting.

Experience Hours (Planning & Scheduling): 
10000
Experience Hours (Cost Management): 
300
Experience Hours (Forensic Analysis): 
500

Graduate Engineer, Planning Engineer, Transmanche Link (TML), Channel Tunnel

START Date: 
August, 1988
END Date: 
December, 1993

Measurement and setting out Engineer on Terminal.

Terminal programme developemnt and progress reporting.

Experience Hours (Planning & Scheduling): 
10000
Experience Hours (Cost Management): 
300
Experience Hours (Forensic Analysis): 
500

Graduate Engineer, Shephard Hill, St Helier Harbour QEII Pier & Fishquay

START Date: 
July, 1986
END Date: 
July, 1987

Shephard Hill

QEII Pier and Fish Quay St Helier Jersey CI

Setting Out / Precast Yard Management / Batching Plant / Materials Laboratory Testing/ 

 

Marine works - dredging - tidal sea bed levels -

Experience Hours (Planning & Scheduling): 
200
Experience Hours (Cost Management): 
50

Graduate Engineer, Shephard Hill, St Helier Harbour QEII Pier & Fishquay

START Date: 
July, 1986
END Date: 
July, 1987

Shephard Hill

QEII Pier and Fish Quay St Helier Jersey CI

Setting Out / Precast Yard Management / Batching Plant / Materials Laboratory Testing/ 

 

Marine works - dredging - tidal sea bed levels -

Experience Hours (Planning & Scheduling): 
200
Experience Hours (Cost Management): 
50

Graduate Engineer, Shephard Hill, St Helier Harbour QEII Pier & Fishquay

START Date: 
July, 1986
END Date: 
July, 1987

Shephard Hill

QEII Pier and Fish Quay St Helier Jersey CI

Setting Out / Precast Yard Management / Batching Plant / Materials Laboratory Testing/ 

 

Marine works - dredging - tidal sea bed levels -

Experience Hours (Planning & Scheduling): 
200
Experience Hours (Cost Management): 
50

Graduate Engineer, Morgan Sindall Infrastructure, Runway Rehabilitation (£31 m)

START Date: 
September, 2014
END Date: 
October, 2014
Assisted project engineers and site management team during night shifts.Completed commissioning and handover documentation.Managed and ensured all snagging works were being completed to acceptable standards by subcontractors.

Graduate Engineer, Morgan Sindall Infrastructure, Terminal 4 Code F Stands (£10m)

START Date: 
October, 2014
END Date: 
December, 2014
Supervised and managed sub-contractors in completing finishing works to successfully handover stands.Booked and maintained detailed records for the site diary.Liaised with end users and stake holders within operational and airline teams.

Graduate Engineer,, Morgan Sindall Infrastructure, Sierra Taxiway Realignment (£20m)

START Date: 
December, 2014
END Date: 
September, 2015
Graduate Engineer, Sierra Taxiway Realignment (£20m) Raised, priced and agreed compensation events.Provided operatives and management with technical assistance.Presented company and project specific inductions.Proposed engineering solutions to problems on site and seeking approval from designers.Compiled information for issuing early warnings and site measures of additional work.Completed quality assurance and non-conformance reports to comply with management systems.Attending planning meetings an

graduate engineer, Oman Power and Water Procurement Company, water and power projects

START Date: 
October, 2017

graduate engineer at the project development depatement. my role involve:

1- assisting and managing the developemnt of new projects in the sector.

2- managing stakeholders.

3- releasing and awarding tenders.

Graduate Engineer, oman power and water procurement company, power and water project developement

START Date: 
October, 2017

Graduate Engineer at Project Developement deparetement.

my role involve:

1- managing stakeholders to the projects.

2- manage and assising the developement of projects.

3- release and evaluate tenders.

Market Place