Acting Planning Manager

Acting Planning Manager, Doosan Babcock, Plant shutdown maintenance

START Date: 
July, 2009
END Date: 
October, 2009

In July 2009 I was sent out to Trinidad to work on a project there for 3 months.  The team consisted of two Mechanical Engineers and me. 

All planning was carried out by me; after the planning was complete I took the role of supervisor.  

In my training I took part in several SMTD courses (Supervisor and Management Training Development)

I also have a license for fork lift operation and a safety passport.

In July (12th to the 14th) I was on a Primavera (P6) training course which I now have a certificate for.

Acting Planning Manager, Veolia, Incineration Plant in Warsaw

START Date: 
July, 2009
END Date: 
March, 2010

EPC JV Leader Planning Level, PM Reporting, Contorl  and coordination

Acting Planning Manager, MOTT MACDONALD LLC, Jumeirah Golf Estates, South Shamkha Infrastrcture

START Date: 
July, 2007
  • Preparation of Strategic Programme & Integrated Project  Master Schedules for all the types of Buildings, Mixed Use Development, Golf Course (Leisure), Aerospace Cluster, Towers, Infrastructure for all phases including Critical path analysis with Oracle Primavera 6.
  • Pre-Construction (Engineering Design/Procurement), Construction and Commissioning, programmes including Critical Interfaces for all types of projects.
  • Forensic Delay Analysis of Claim submissionby the Contractor for Extension of Time recommendation

Acting Planning Manager, Modern Executive System Contracting , Several Commercial and Residential Projects

START Date: 
December, 2007
END Date: 
April, 2009

·         Provide comments and recommendations for planning and scheduling requirements relative to staffing and project controls..

·         Assist in reviewing proposal provisions related to schedule and material control, and develop supporting data for contract negotiations.

Experience Hours (Planning & Scheduling): 
2650
Experience Hours (Cost Management): 
2650
Experience Hours (Forensic Analysis): 
2650

Acting Planning Manager, Trinitrain, TTRT

START Date: 
June, 2009
END Date: 
May, 2010

Planning engineer on a railway Construction Project

WBS creation, Planning construction and development, resources assignment, S Curves and histogram construction, progress report and critical path analysis.
Interface Management

Experience Hours (Planning & Scheduling): 
2000

Acting Planning Manager, CEG Consultant Engineering Group, EBSD

START Date: 
June, 2008

Consultant Engineering Group (CEG)From 19 Jun 2008 Up to Present as senior planning Engineer in Engineering Business Supporting Department in Public Work Authority. Lead of planner team to

·  evaluate the projects variations and EOT

·  Reviewing the new projects baseline programs

·  Creating Data Base For Document Control 