Website Upgrade Incoming - we're working on a new look (and speed!) standby while we deliver the project

Van Oord via Minstrell Recruitment

Freelance Senior Planner, Van Oord via Minstrell Recruitment, Liverpool 2 Container Berth

START Date: 
March, 2014

March 2014 – date - Ross Planning contract for Van Oord via Minstrell Recruitment – Liverpool 2 Container Berth, analysis in P6, ChainLink, comment & updating

Analysis of Bam Nuttall P6 programme for JV partner Van Oord for new container berth, using past marine experience. Also using ChainLink time-chainage and provide a high-level report on the effect of current piling delays, nominally on a day per week basis after initial input. Work started comparing Issue 8 with previous issues, then roughly monthly updates.

Market Place

No results found... (try selecting a different content filter)

Syndicate content