Website Upgrade Incoming - we're working on a new look (and speed!) standby while we deliver the project

UGL Resources

Senior Planner, UGL Resources, RGP5; RGP6, LYNAS RARE EARTHS PROJECT – Design

START Date: 
April, 2010
END Date: 
September, 2012

·         Worked with a team of planners on RGP5 Project and was also the designated shutdown planner for managing pre-shut works and shutdown works on 12 shuts. These shutdowns were implemented successfully according to the client.

·         Was involved on Lynas Rare Earths Construction Project for some months.

·         Also supported the bid team for tendering with developing schedules and assisting with manpower estimating.

Experience Hours (Planning & Scheduling): 
3900
Experience Hours (Cost Management): 
300
Experience Hours (Forensic Analysis): 
400

Principle Projects Planner, UGL Resources, LYNAS RARE EARTHS PROJECT – Design, Procure, Construct, Commission of Advanced Rare Earths materials plant project in Malaysia.

START Date: 
January, 2010
END Date: 
March, 2011

Projects Planner,1/2010 to 3/2011

Development of fully integrated Design, Procure and construction schedule.

Selected Accomplishments:

Implemented data process to take UGL Estimate values as Design engineering progressed into Procurement and Construction schedules. This included adding the schedule coding in reverse back into estimating system and 3D design models.

Experience Hours (Planning & Scheduling): 
450
Experience Hours (Cost Management): 
100

Market Place

No results found... (try selecting a different content filter)

Syndicate content