SINCLAIR KNIGHT MERZ - SKM

Forensic Planner / Delay Analyst, SINCLAIR KNIGHT MERZ - SKM, Dampier Fuel Warf Project

START Date: 
August, 2011
END Date: 
October, 2011

Dampier Fuel Warf Project Marine & Piping Expansion Project in Dampier.

Forensic Planner, (Specific Assignment), 08/2011 to 10/2011

EOT Defense review for owner against construction contractor due to drawing delivery delay and access delay.

Experience Hours (Forensic Analysis): 
250

ROLANDO LACAP

First Name: 
ROLANDO
Last Name: 
LACAP

PERSONAL DATA:

NATIONALITY               Australian

SEX                             Male
CIVIL STATUS               Married
 

EDUCATIONAL ATTAINMENT:
ELEMENTARY           &nbs

Professional Since: 
Mar-2000 (24.8 yrs experience)
Oldest experience: 
Aug 2009 (15.4 yrs experience, WARNING: 9.4 years variance with Professional Since)
Years Experience: 
45

Project Controls Leader, SINCLAIR KNIGHT MERZ - SKM, EPMC for the first phase of the Coke Mine's expansion at Cerrejon, Guajira.

START Date: 
June, 2012
END Date: 
May, 2014