MALAYSIA MARINE & HEAVY ENGINEERING SDN BHD

Site Planning Engineer, MALAYSIA MARINE & HEAVY ENGINEERING SDN BHD, Gumusut Kakap Offshore Platform Development

START Date: 
June, 2007
END Date: 
May, 2008

1. Prepared and updated workpack and jobcard for Fabrication of Gumusut Kakap Floating Production System

2. Monitored and maintained benchmarking for each fabrication discpline

Experience Hours (Planning & Scheduling): 
2000

Lead Planning Engineer, Malaysia Marine & Heavy Engineering Sdn Bhd, SEADRILL T11/ T10 - Self Erecting Drilling Tender Barge Project

START Date: 
November, 2006
END Date: 
February, 2007

SEADRILL T11/ TIOMAN T10 - Self Erecting Drilling Tender Barge Project – Malaysia ($120M - 8,000MT)

  • Handed over successfully with client acceptance of two (2) units Self-Erecting Drilling Tender Barge.
  • Compiled and turnover every project deliverables and reports to client; final progress report, as-built drawings, and operation & maintenance documentations.
Experience Hours (Planning & Scheduling): 
700
Experience Hours (Cost Management): 
700
Experience Hours (Forensic Analysis): 
700