Maintance System Solutions

Planner, Maintance System Solutions, Oil & Gas Projects

START Date: 
September, 2009
END Date: 
July, 2011

I performed initial schedule preparation (WBS, setting up calendars), breakdown of activities and budgeting, resource levelled the schedule to match staffing plan plus capitalize on available schedule float. Maintained project schedule baseline, and updated baseline. Prepared data for daily project meeting to review performance indicators, variances, and critical path. Project meeting preparation included reviewing schedule variances and critical path impact.