Madrid (Spain)

QC CONSULTANT ENGINEER , UMI /ZWICK /IBERTEST, Madrid (Spain) , GE Plastics Lab, Siderurgica Sevillana Still Mill Lab.

START Date: 
March, 2003
END Date: 
November, 2008

Consultant Engineer of materials testing and Quality Controls Equipment assessments under industrial standards as ISO, ASME, and AENOR.

AC inspection and QC gauges for civil/ mechanical/ steel mill companies in Spain.

Sales budget of 6 Million Euros per year for material testing machines and QC laboratories.

Representing Sales Engineer for many of the most important manufacturers of the world as Zwick, Toni Technik, Roëll Kortaus, Ibertest, UMI, MTS, Instron, etc.  

LEAD PLANNING ENGINEER , ABENGOA (BEFESA AGUA), Madrid (Spain), EPC project of desalinization plant of Ténès (Algeria), EPC project of desalinization plant of Honaine (Algeria)

START Date: 
December, 2008
END Date: 
January, 2010

EPC project of desalinization plant of Ténès (Algeria) with a budget of 240 Million USD with a design specification for desalinization water rate of 200.000 m3 of potable water per day for 2 million people in the Nord of Algeria.

EPC project of desalinization plant of Honaine (Algeria) for the JV company between Abengoa and Sacyr with a budget of 180 Million USD with a design specification for desalinization water rate of 180.000 m3 of potable water per day for 1.5 million people in the Nord of Algeria.  

PROJECT CONTROLS MANAGER , INTECSA (ACS Group), Madrid (Spain), Flare Gas Recovery Revamping TAKREER, International tender proposals, MBAC Refinery & Bauxite Mine

START Date: 
March, 2012
END Date: 
June, 2013

Project Controls Manager of the Lump Sum Projects for the Flare Gas Recovery Revamping of  TAKREER (Abu Dhabi Oil Refinery Company) on both of Ruwais & Abu Dhabi Refineries with a budget around of 40 million USD.