Valencia Water Reclamation Plant, Stage Five. Worked as a Project Engineer constructing the $40M water treatment plant expansion for LA County Sanitation. Developed and maintained construction cost and resource loaded baseline schedule comprising over 5,000 schedule activities. Prepared monthly schedule submittals and progress payment requests.