Planning Engineer, Hindustan Construction Company Limited, Lucknow – Muzaffarpur National Highway|4 Lanning from km 8+250 to 93+075 of Lucknow – Ayodhya Section of NH-28 [Package - LMNHP: EW-II (WB)-1 and 2]

START Date: 
October, 2005
END Date: 
July, 2006

·   Played a vital role in the construction of 85km flexible and rigid pavements; cross drainage works, major and minor bridges, an underpass, flyover, railway over bridge and highly complex interchanges 

Experience Hours (Planning & Scheduling): 
1600
Experience Hours (Cost Management): 
800
Experience Hours (Forensic Analysis): 
400