I compile ASTA programmes alongside the Project Managers and update with weekly progress. I export various reports from ASTA to the directors and to the site team as well as internal department heads.
I report on delays within Design, Procurement, In House Manufacture and Installation.
I complie 2 week lookahead programmes using the ASTA filter options
I report on both Jagged line and straightline (rescheuled programmes)
I also use ASTA to report on Factory resource availability showing over and under allocation.