“Kazakhstan Caspian Offshore Industries” LLP

Offshore Planner, “Kazakhstan Caspian Offshore Industries” LLP, Kashagan Field Development Experimental Program - Hook-up & Commissioning of Complex D & Island A Offshore Facilities - Temporary Refuge Barge (TRB)

START Date: 
July, 2011
END Date: 
March, 2012

v  Prepare, maintain and control integrated lower level progress measurement system.

v  Visited the project site regularly for periodic progress report and evaluation.

v  Worked with Project Manager for support in the productive and timely completion of the project.

v  Attended progress meetings and reported on the project situation.

Experience Hours (Planning & Scheduling): 
800
Experience Hours (Forensic Analysis): 
1500

Kuanysh Bekbauov

First Name: 
Kuanysh
Last Name: 
Bekbauov
Oldest experience: 
Aug 2010 (14.6 yrs experience, WARNING: 40.6 years variance with Professional Since)
Years Experience: 
2

PLANNING ENGINEER, “Kazakhstan Caspian Offshore Industries” LLP , Kashagan Field Development Project EP Offshore. Mechanical Completion

START Date: 
January, 2012

 

·         Planning and schedule preparation for engineering, procurement, construction of Mechanical, Piping and Electrical, Instrumentation activities

·         Responsible for monitoring progress of work and compares with the approved schedule.

·         Daily monitoring the Status of Subsystems and Commissioning Units (ITR’s, DAC’s, MC-01 completion)