Planning & Scheduling through the Gates

7 years 31 weeks ago

Project planning and scheduling processes follow a management framework called the Project Implementation Model (PIM). Such model divides the project into sub-boundaries called stages, gates, or checkpoints.

Does not really matter what proprietary term they call it. Company Y can call it Y-PIM (Company Y Implementation Model). Construction firm ABC might call theirs ABC-PIM.

Read more...
 

Risk-based Management Framework

7 years 32 weeks ago

A project management framework is important in effectively managing projects. Planning and scheduling management framework is essential in managing plans and schedule. An engineering management framework governs engineering works as does a safety management framework provide standards and guidance to all safety works.

In these frameworks lie processes that are fundamental to each

Read more...
 

Project Management: Centralized vs. Decentralized Delivery

7 years 33 weeks ago

There is an ongoing dialogue in many enterprises: Should project management be a centralized, shared-service?  Or, should project managers be decentralized and embedded within their functional organizations? 

The answer is, "it depends."  Every enterprise is unique with its own organizational structure, culture, expectations, and needs.  Similarly projects and

Read more...
 

The USACE CPM Schedule Specification

7 years 36 weeks ago

The Specification is full of errors and is biased in favor of specific software.

Just take a look at a few sections, it is a disaster.

2.1 SOFTWARE - 2.1.2.2 Other Than Primavera - If the contractor chooses software other than Primavera P6, that is compliant with this specification, provide for the Government's use two licenses, two computers, and training

Read more...
 

Reorganizations: Managing Your Feelings

7 years 37 weeks ago

A phrase heard at many organizations is, “The only constant is change.” Reorganizations, restructurings, and layoffs have become a regular event. These events reshape the work-landscape at the individual and team level:

  • Friends and colleagues may move to other groups within the company or leave;
  • You may have a new management team with whom you need to build rapport and trust
Read more...
 

How Early and Late date are calculated in Start to Start relationship in Primavera P6

7 years 40 weeks ago

In Finish to Start relationship, Primavera calculate Early and Late date base on 2 process

  • Forward Pass (to calculate Early Start and Early Finish)

Read more...
 
Primavera P6

Recommended Steps to Effective Gate 1 IAP

7 years 41 weeks ago

Interactive Planning (IAP) is a methodology used by projects to engage important stakeholders and subject matter experts in a facilitated workshop setting.

The engagement process is through collaborative discussion of project plan and strategy to develop a reliable, complete, and successful project schedule. Interactive Planning is also widely known as Participative Planning (PP).

Read more...
 

Powerful Words, “I Don’t Know”

7 years 42 weeks ago

“I don’t know” are three words that most people dread saying.  The need to know the answer has followed us from school into the working world.   We are loath to admit ignorance.  I have seen colleagues twist themselves into a pretzel inventing an answer.

Providing incorrect information may have negative consequences, including:

  • Something may be done wrong
Read more...
 

Guide to Gate 1 Interactive Planning

7 years 43 weeks ago

Interactive Planning (IAP)

Interactive Planning (IAP) is a methodology used by projects to engage important stakeholders and subject matter experts in a facilitated workshop setting.

The engagement process is through collaborative discussion of project plan and strategy to develop a reliable, complete, and successful project schedule.

Interactive Planning is also widely

Read more...
 

Making Sense of Agile

7 years 45 weeks ago

There has been a tectonic shift in how software is developed.  Terms like Agile, CI/CD, DevOps, BDD, and TDD are new additions to the IT vocabulary. 

These new practices and related tools promise to significantly reduce the time and effort required to build, test, and deploy software.  Leading companies modify their applications daily and regularly push updates to their

Read more...
 