Revision of Network Rules from Sun, 2009-03-08 14:22
When building your activity network, the following items are concidered Best Practice...
PLEASE ADD TO, OR AMEND THIS LIST...
- All tasks / activities have predecessor and successor
- All tasks / activities have at least one Finish-to-Start successor
- Resources are assigned to tasks / activities and not summary activities
- Milestones do not have resources / budget (a milestone does not have scope)
- Thou shall not have negative lag on a task / activity. Most people are pretty soft on that, but general opinion is that negative lag predicts the future with certainty and that is poor logic
- GoldyLocks was right - tasks are not too long or too short, they have to be "just right" in duration. You have to decide what that means and set sensible / justifiable durations.
- Too much positive lag on a task probably indicates missing tasks
- Constraint types: You want them to be As Soon As Possible as much as you can. Start-No-Earlier-Than, Finish-As-Late-As-Possible, and Finish-No-Earlier-Than are tolerable. Items like Must-Finish-On, Must-Start-On, Finish-No-Later-Than, Start-No-Later-Than are pretty much not a good thing.
- Check your logic
- Every activity gets a baseline