Revision of Hammock Tasks from Sun, 2009-03-08 14:02
A hammock task is dependent on external dates for its start and finish dates and, ultimately, its duration.
The name, hammock task, is derived from the way a hammock's shape is determined by the distance between the points to which it is attached.
- Create the task to become the hammock.
- Go to the task that will drive the start date of the hammock and create a [Start-to-Start ]relationship with the hammock.
- Go to the task who's finish will drive the compltion of the hammock and create a [Finish-to-Finish] relationship with the hamock.
By doing this, the hammock (sumary) activity will be representative of the underlying / linked set of activities.