Installation Sequences

Industrial and Commercial installations usually commence when false ceilings, floorings and final decorations are substantially complete. 

Kitchen Hood Installations are done before false ceiling completion and kitchen equipment is done after the civil wall&floor finishes.

Installation Periods 

 

Size Of Kitchen

Are of Kitchen

Installation Time

100 people

50 m2

3 weeks

500 people

150 m2

5 weeks

1,000 people

275 m2

8 weeks

 For individual installations...

 Ovens, friers and large mixers etc = 1 man day per item

Sinks, bain maries, washers etc = 2 man days per item


 

 