Revision of Covered Steel Footbridge from Sun, 2009-02-08 12:54
Simple universal beam steel bridge in modular sections, welded on site. 16 truss sections each 15 m in length, supported on H-frame vertical columns / supports.
- Support Steelwork Fabrication (4 bays) = 25 days
- Support Steelwork Erection (4 bays) = 30 days
- Truss erections (4 bays) = 18 days
- Paintwork To Steel (16 bays) = 35 days
- Bridge Deck Concrete Works (16 bays) = 60 days (staggered)
- Bridge Lighting, Roof etc (16 bays) = 40 days
- Bridge Finishing, Handrails and Grano = 14 days