Hollorib Decking
Lay decking = 350 m2/day
Shear Connecting Studs 235 m2 studded per day per gun (4,000 studs/week)
Concrete topping = 4,000 m2/week or 2,000 m2/week incl power floating
No results found... (try selecting a different content filter)
Email: PPadmin@planningplanet.com