Revision of
Hollorib Decking
from
Sat, 2009-02-07 16:18
Posted Sat, 2009-02-07 16:18 by Technical Develop...
Hollorib Decking Lay decking = 350 m2/day Shear Connecting Studs 235 m2 studded per day per gun (4,000 studs/week) Concrete topping = 4,000 m2/week or 2,000 m2/week incl power floating
‹ Formwork Re-Use
up
Raft formwork ›
Login
or
register
to post comments
Market Place
No results found... (try selecting a different content filter)
Top Posters
Rafael Davila
5,241 posts
Mike Testro
4,418 posts
Zoltan Palffy
3,089 posts
Vladimir Liberzon
2,753 posts
Rodel Marasigan
1,699 posts
Samer Zawaydeh
1,664 posts
Anoon Iimos
1,422 posts
Alexandre Faulx-B...
1,355 posts
Dieter Wambach
1,350 posts
Charleston-Joseph...
1,347 posts
Contact Us
Email:
PPadmin@planningplanet.com
User login
Username or e-mail:
*
Password:
*
Create new account
Request new password
Partners & Sponsors
Website Development by Hunt Data Solutions and Vit-al Interactive. CMS:
Drupal
THEME:
Acquia Marina