Revision of Waffle Flooring from Sat, 2009-02-07 17:12
Rate includes for erection of decking and infill beams, cut position & nail plywood ribs, transport position and fix 800 mm x 800 mm waffle forms, clean and oil plywood and adjust to levels (m2/hr).
Conservative Erection Rate...
- 2.4 m grid, ne 3.5 m high soffit = 1.42 m2/hr
- 3.5 - 5.5 m high soffit = 1.13 m2.hr