Revision of Bituminous Waterproofing from Sat, 2009-02-07 15:54

Brush applied coatings (tretol etc) to prepared concrete surfaces.
  • A two coat application = 5.0 m2/hr
  • A three coat application = 3.5 m2/hr
Sheet materials (bituthene etc) fixed to prepared concrete surfaces.
  • Horizontal Surfaces = 4.0 m2/hr
  • Vertical Surfaces = 3.5 m2/hr