Website Upgrade Incoming - we're working on a new look (and speed!) standby while we deliver the project

Planner, Schofield Lothian, RMG A13 JV DBFO Road Claim v TFL

START Date: 
February, 2005
END Date: 
March, 2006

Joined Schofield Lothian to gain experience as a Forensic Planner based in Central London.

Slough Borough Council v Dew Pitchmastic, Slough, UK

Worked as the delay analyst for Schofield Lothian providing forensic planning support to the defendant SBC during the refurbishment of a residential tower block. The contractor was requesting an extension of time

Birse Build Ltd v Elliotts Brickwork, Hemel Hempstead, UK

Worked as the delay analyst providing planning support for claims which included preparing as-built programmes for 3 No. apartment blocks.

RMG A13 Joint Venture DBFO Road claim v Transport for London (TFL), Canning Town, UK

Worked in a team of delay analysts doing forensic planning gathering evidence to develop as-built programmes for four phases of heavy civils work. Exercises completed to compare deliveries of materials against the as-built dates for activities.

Munns Electrical v Mitie, UK

Worked as the delay analyst collating as-built programmes and then broking them down to develop more detailed versions.

TAG v Aggregate Industries, Farnborough Airport, UK

Worked as the delay analyst carrying out an impaction exercise to see how the compensation events affected the contract programme to illustrate an extension of time for Aggregate Industries.

Experience Hours (Forensic Analysis): 
2200