Lead Planning & Scheduling Engineer , Shair & Partners, Khafji Field Development Plan, Phase 1
START Date:
May, 2007
END Date:
November, 2008 Khafji Field Development Plan, Phase 1 Design & construction of offshore platforms (Y1-B and Y2-B) & flow stations, 36" undersea Crude Oil Transmission Line from Y2-B and 42" undersea Gas Transfer line from Y2-B intrafield Oil & Gas gathering lines, On-shore Inlet Separator System and On-shore Gas Compression & Processing Facilities. The projects also included installation of three (3) Power Distribution Platforms (PDP) & one (1) IWJ-5.
- Company:
- Industry:
- Job Role:
- Project:
- Region:
- Skills & Expertise: