Planning Manager, New World Construction Limited, Tai Wai Station
START Date:
March, 2016 How to show the Scheduled % of work for a group of activities.
Cannot show under the WBS Group.
Put all activites under the same WBS and add an activites (WBS summary).
Then it can show the scheduled % for the group of activites.
Experience Hours (Planning & Scheduling):
3000
Experience Hours (Cost Management):
500
Experience Hours (Forensic Analysis):
1000 - Company:
- Industry:
- Job Role:
- Project:
- Region:
- Skills & Expertise: