Supervising Project Controls Specialist/Project Controls Lead, WSP|Parsons Brinckerhoff, Eastlink Final Design I90 LRT project in Seattle
START Date:
May, 2015
END Date:
December, 2015 - .
WSP | Parsons Brinckerhoff, Seattle, WA (2015)
:
This project entails modifications to 6.9 miles of the existing Interstate 90 highway – including a floating bridge and two tunnels.
Position Scope:
- Assisted Project Management with planning and development of change orders, PCR’s, variance reports, and final proposed change order, for scope and budgets.
- Developed a new contractual final design schedule as a baseline in advancement of 90% design per final signed CTC.
- Produced Monthly Progress update.
- Supervised Estimating and Construction task for Cost Estimators and Construction Schedule. Reviewed Construction Schedule in support of GCCM MACC contract negotiations.
- Developed early contract breakout packages from the 60% construction schedule for early procurement completion timeframes for design to the GCCM construction contractor per the contracts.
- Supervised project admin staff for WBS snapshot and invoices costs for project team. Monitored task actuals, change control log, and new change management PCR’s.
- Verified Scope for third party reviews with various agencies and monitored deliverables for contract review times for timely reviews.
- Provided project status information and support to the Project Manager, design manager, and client.
- Produced 675-line cost loaded design baseline schedule with a $21 M design budget for a June 16, 2016 90% design and Dec 14, 2016 100% design completion dates.
Experience Hours (Planning & Scheduling):
1150
Experience Hours (Cost Management):
150
Experience Hours (Forensic Analysis):
100 - Company: