Head of Planning and Project Control, OIEC, Gas Gathering and NGL Recovery
START Date:
December, 2005
END Date:
June, 2007 Project 1: Sirri Island Gas Gathering & NGL Recovery (458 million USD project)
Title: Head of Planning & Project Controls (At Site) (Dec 2005 to Jun 2007)
Duties: Responsible for a team of 3 people in planning & project control activities in Sirri Island performed By OIEC as the main contractor of Iranian Offshore Oil Company (IOOC) as the client, in this EPC Project I was specifically responsible for all the related affairs regarding to the project construction Planning & controls activities such as reviewing sub-contractor plans and modify them based on Project master schedule, preparing Daily, Weekly & Monthly Reports, and FDCC.
- Company:
- Industry:
- Job Role:
- Project: