Schedule Control, POSCO E&C / Ventanas Philippines Contructions Inc., 300 MW Coal Fired Power Plant Expansion EPCC Project
START Date:
October, 2016 Schedule Control, Claims Analysis, Schedule Analysis, Progress Reporting, Site Trackiing and Monitoring, Time IMpact Analysis
Experience Hours (Planning & Scheduling):
4150 - Company:
- Industry:
- Job Role:
- Project:
- Region: