Project planner and Cost control, Holtec Consulting Private Limited, Construction of 10000 TPD Cement Plant

START Date: 
June, 2006
END Date: 
July, 2007

The job responsibilities included:

  1. Preparation of Master Schedule using Primavera P3 for new cement plant and its split grinding units
  2. Provide planning and cost controlling support for all projects which includes variation reporting, monitoring of milestone progress to the preparation of customer billing processes.
  3. Perform project costing related reporting to the team and management’s review on a monthly basis to ensure that expenditures are kept within the project budget.
  4. Coordinate with Site manager and Unit supervisor for daily job progress and capacity planning.
  5. Preparation of Project performance indicators (such as CPI, SPI).
  6. Critical activities monitoring and preparation of forecast and trending curves
  7. Monthly updating of Project & Construction S-Curves for all packages, percentage progress reporting for MSR & updating of planning procurement muster every month.
  8. Review the site activities along with client and update forecast trends.
Experience Hours (Planning & Scheduling): 
900
Experience Hours (Cost Management): 
150
Experience Hours (Forensic Analysis): 
350