Head Planner & Controller, MAPNA, Yazd Solar Thermal Power Plant (2x159MW Gas, 1*132MW Steam, 17MW Solar)

START Date: 
November, 2005
END Date: 
December, 2007

 

                      ·   Execution Strategy

                      ·   Level 2 time schedule

                      ·   WBS (Basic & Detail Design, Tendering, Supply/Manufacturing, Transportation, Civil, Erection & Commissioning)

                      ·   Weight percent of each above

                      ·   Level 3 time schedule (Basic & Detail Design, Tendering, Supply/Manufacturing, Transportation, Civil, Erection & Commissioning Activities)

                      ·   Check & approve WBS (include weight percent) of subcontractors

                      ·   Check & approve level 4 time schedule of subcontractors

                      ·   Monthly progress report (S-Curve (Plan, Actual & Forecast), Updated level 3 time schedule, critical path & critical activities)

                      ·   Site visit