Head Planner & Controller, MAPNA, NEKA Combined Cycle Power Plant (1x160MW)

START Date: 
November, 2002
END Date: 
July, 2006

 

                      ·   Execution Strategy

                      ·   WBS (Basic & Detail Design, Tendering, Supply/Manufacturing, Transportation, Civil, Erection & Commissioning)

                      ·   Weight percent of each above

                      ·   Level 3 time schedule (Basic & Detail Design, Tendering, Supply/Manufacturing, Transportation, Civil, Erection & Commissioning Activities)

                      ·   Key milestones

                      ·   Check & approve WBS (include weight percent) of subcontractors

                      ·   Check & approve level 4 time schedule of subcontractors

                      ·   Monthly progress report (S-Curve (Plan, Actual & Forecast), Updated level 3 time schedule, performance report, critical path & critical activities)

                      ·   Site visit