Head Planner & Controller, MAPNA, NEKA Combined Cycle Power Plant (1x160MW)
· Execution Strategy
· WBS (Basic & Detail Design, Tendering, Supply/Manufacturing, Transportation, Civil, Erection & Commissioning)
· Weight percent of each above
· Level 3 time schedule (Basic & Detail Design, Tendering, Supply/Manufacturing, Transportation, Civil, Erection & Commissioning Activities)
· Key milestones
· Check & approve WBS (include weight percent) of subcontractors
· Check & approve level 4 time schedule of subcontractors
· Monthly progress report (S-Curve (Plan, Actual & Forecast), Updated level 3 time schedule, performance report, critical path & critical activities)
· Site visit